| Tasks |
Responsible |
Time estimated |
status |
| Upgrade of CAENET driver on
na58pc037 and OS upgrading to RedHat 7.3. Test of SLiC with new driver |
I. Manouilov, V. Falaleev |
2 weeks |
done on December 03 |
| Integrate Lecroy PS for
Trigger |
I. Manouilov |
1 month + 3 weeks |
postponed |
| Integration of Alerts from
Micromegas and Drifts using Channel Access |
D. Sora |
1 month |
done on
March 04 |
| Control of ISEG PS for
STRAWs by SLiC OPC server |
D. Sora |
4 weeks + 1 week PVSS |
done on May
04 |
| Control of ISEG PS for
Silicons by SLiC OPC server |
D. Sora |
4 weeks |
done on May
04 |
| Pass information to/from
SLiC by group instead of by channel |
D. Sora |
2 months |
postponed |
| Replacement of Wiener
Fantrays control |
V. Falaleev |
2 weeks |
done on May
04 |
| Integration of RICH Wiener
LV, using OPC server |
V. Falaleev |
2 weeks |
ongoing |
| Integration of 3 Wiener LV
crates for STRAWs |
V. Falaleev |
1 month |
ongoing |
| Control of temperature and
humidity for STRAWS |
M. Varanda |
4 weeks (hw) + 2 weeks
(PVSS) |
done on
December 03 |
| Cold Silicon temperatures |
M. Varanda + C. Quintans |
2 weeks (PVSS) |
done on
October 04 |
| Monitoring of Gas system for
MW1 from PLC3 |
C. Quintans |
2 weeks |
done on June
04 |
| Monitoring of Gas system for
Silicons |
M. Varanda |
3 weeks |
- |
LV monitoring and crates
control for MW1 |
M. Varanda |
2 weeks |
done on May
04 |
| NIM crates control for
Trigger |
M. Varanda |
1 month |
ongoing
-
waiting for
cables from trigger group |
| Monitoring of RICH Wall LV
and HV |
? |
? |
hardware postponed |
| Monitoring of Target magnets
via ELMB |
M. Varanda |
1 week |
done on May
04 |
| Additional temperature
sensors for MM |
M. Varanda |
3 weeks |
done on
April 04 |
| Additional temperature
sensors for DC |
M. Varanda |
2 weeks to build and install
boxes + 1 week PVSS |
ongoing |
| Additional temperature
sensors for RICH |
M. Varanda |
1 week |
ongoing |
| CAEN HV and LV channels
control for GEM11 |
C. Quintans |
2 weeks |
done on May
04 |
| Control of 1 additional CAEN
crate for Silicon |
C. Quintans |
1 week |
done on May
04 |
| Temperature sensors for W45 |
M. Varanda |
3 weeks |
done on May
04 |
| Additional LV for W45 |
M. Varanda |
1 week |
done on May
04 |
| Monitoring of Gas
distribution system status |
M. Varanda |
2 weeks |
done on May
04 |
| Control of CAEN HV modules
for Veto Box |
C. Quintans |
1 week |
done on June
04 |
| Monitoring of HV status for
Veto Box via ELMB |
M. Varanda + C. Quintans |
3 weeks |
done on
October 04 |
| Integration of 2 CAEN HV
crates for BMS |
C. Quintans |
1 week |
done on June
04 |
| Segmentation of CAEN HV for
RICH |
C. Quintans |
1 week |
done on June
04 |
| Integrate SM2 interlock
signal |
- |
- |
postponed |
| Integrate
CAEN modules for RICH electronics prototypes |
C. Quintans |
1 week |
done on October 04 |
| Replace display of DpNames
by DpAlias for ELMBs and some other datapoints |
C. Quintans |
- |
done on
March 04 |
| Replace Action buttons in
ELMB panels, display of units where absent |
C. Quintans |
2 weeks |
done on
March 04 |
| Revision of ELMB hardware |
M. Varanda, V. Falaleev |
1 month |
done |
| Cleaning error/warning
messages from log files |
C. Quintans + IT/CO |
2 weeks |
ongoing |
| Revision of spare DCS
hardware |
V. Falaleev |
until end 2003 |
done |
Document any new or past
developments |
all |
? |
- |
| Install new versions of PVSS
and Framework |
all |
1 month |
postponed for after 2004 run |